THE EFFECT OF TIMELY DELIVERY OF CONSTRUCTION PROJECTS ON THE ECONOMIC DEVELOPMENT OF NIGERIA ( A CASE STUDY OF SOME SELECTED PROJECT SUPERVISORS IN JULIUS BEGER PLC AND MARLUM CONSTRUCTION COMPANY) | Blazingprojects Postgraduate Thesis
Home / Civil engineering / THE EFFECT OF TIMELY DELIVERY OF CONSTRUCTION PROJECTS ON THE ECONOMIC DEVELOPMENT OF NIGERIA ( A CASE STUDY OF SOME SELECTED PROJECT SUPERVISORS IN JULIUS BEGER PLC AND MARLUM CONSTRUCTION COMPANY)

THE EFFECT OF TIMELY DELIVERY OF CONSTRUCTION PROJECTS ON THE ECONOMIC DEVELOPMENT OF NIGERIA ( A CASE STUDY OF SOME SELECTED PROJECT SUPERVISORS IN JULIUS BEGER PLC AND MARLUM CONSTRUCTION COMPANY)

 

Table Of Contents


Chapter ONE

INTRODUCTION

  • 1.1Introduction
  • 1.2Background of Study
  • 1.3Problem Statement
  • 1.4Objective of Study
  • 1.5Limitation of Study
  • 1.6Scope of Study
  • 1.7Significance of Study
  • 1.8Structure of the Research
  • 1.9Definition of Terms

Chapter TWO

LITERATURE REVIEW

  • 2.1Overview of Timely Delivery in Construction Projects
  • 2.2Economic Impact of Timely Delivery
  • 2.3Factors Affecting Timely Delivery
  • 2.4Best Practices in Timely Delivery
  • 2.5Case Studies on Timely Delivery
  • 2.6Technology and Timely Delivery
  • 2.7Stakeholder Involvement in Timely Delivery
  • 2.8Environmental Implications of Timely Delivery
  • 2.9Legal Aspects Related to Timely Delivery
  • 2.10Global Perspectives on Timely Delivery

Chapter THREE

SYSTEM DESIGN AND IMPLEMENTATION

  • 3.1Research Methodology Overview
  • 3.2Research Design and Approach
  • 3.3Data Collection Methods
  • 3.4Sampling Techniques
  • 3.5Data Analysis Procedures
  • 3.6Ethical Considerations
  • 3.7Reliability and Validity
  • 3.8Limitations of the Methodology

Chapter FOUR

SYSTEM TESTING AND EVALUATION

  • 4.1Overview of Research Findings
  • 4.2Timely Delivery Practices in Construction Firms
  • 4.3Economic Benefits of Timely Delivery
  • 4.4Challenges Faced in Achieving Timely Delivery
  • 4.5Comparison of Timely Delivery Strategies
  • 4.6Stakeholder Perspectives on Timely Delivery
  • 4.7Recommendations for Improving Timely Delivery
  • 4.8Implications for Future Research

Chapter FIVE

SUMMARY, CONCLUSION AND RECOMMENDATIONS

  • 5.1Summary of Findings
  • 5.2Conclusion
  • 5.3Recommendations
  • 5.4Contribution to Knowledge
  • 5.5Areas for Future Research

Thesis Abstract

Abstract
Timely delivery of construction projects plays a crucial role in the economic development of Nigeria. This study aimed to investigate the effect of timely project delivery on economic development, focusing on selected project supervisors in Julius Berger PLC and Marlum Construction Company. The research employed a mixed-methods approach, combining quantitative data analysis and qualitative interviews to gain a comprehensive understanding of the subject. The findings revealed that timely delivery of construction projects positively influences economic development in Nigeria. Projects completed on time contribute to increased investor confidence, attract foreign direct investment, and stimulate overall economic growth. Additionally, timely project completion enhances the reputation of construction companies, leading to more opportunities for future projects. The study also identified various factors that impact project timeliness, including effective project management, adequate funding, skilled labor availability, and government policies. Project supervisors highlighted the importance of proper planning, resource allocation, and stakeholder collaboration in ensuring timely project delivery. Challenges such as delays in material procurement, changes in project scope, and unforeseen site conditions were also noted as significant barriers to timely completion. Recommendations were provided based on the research findings to improve the timeliness of construction projects in Nigeria. These recommendations include implementing stricter project management practices, enhancing collaboration among project stakeholders, improving the procurement process for construction materials, and investing in training programs to upgrade the skills of construction workers. Government agencies were advised to streamline approval processes, provide incentives for timely project completion, and enforce regulations to minimize delays. Overall, the study underscores the critical role of timely project delivery in driving economic development in Nigeria. By addressing the challenges identified and implementing the recommended strategies, construction companies like Julius Berger PLC and Marlum Construction Company can enhance their contributions to the economy, attract more investment opportunities, and foster sustainable development in the country.

Thesis Overview

INTRODUCTION1.1 BACKGROUND OF THE STUDY Time impacts are inevitable on construction projects, primarily because of the uniqueness of each project and the limited resources of time and money that can be spent on planning, executing and delivering the project. Time factors are inherent in all of project construction’s undertakings. Construction projects have long been recognized as particularly cost, time and risk-laden. Some of the time and cost factors associated with the construction process are fairly predictable or identifiable; others may be totally unforeseen. The constructed project may not perform as anticipated because the owner may have unrealistic expectations regarding the delivery time of construction forcing contractors into unrealistic gambles, corner-cutting or commitments that may not be realistic (Frimpong 2003). Project success can be defined as meeting goals and objectives as prescribed in the project plan. A successful project means that the project has accomplished its technical performance, maintained its schedule, and remained within budgetary costs. Project management tools and techniques play an important role in the effective management of a project. Therefore, a good project management lies in the management tools and techniques used to manage the project. Project management involves managing the resources—workers, machines, money, materials and methods used. Some projects are effectively and efficiently managed while others are mismanaged, incurring much delay and cost overruns and negatively affecting the economy (Frimpong 2003). Assessing construction projects’ delivery time is critical in today’s market-driven economy. To improve the economy and maximize long-term return on this public investment, government agencies have recently started utilizing new types of contracting methods that are designed to achieve multiple project objectives, including minimizing construction cost and duration, while maximizing its quality. In recent years, many departments of transportation, in various states have started to apply new highway contracting methods, including: Bidding on time i.e., to encourage competition among contractors to minimize project duration (Holt et al 2000), Incentive/ disincentive contract clauses that provide financial incentives to reduce construction duration, Night time construction that seeks to cut service disruption and project time by requiring contractors to work during off-peak night time hours, Warranty contracting that attempts to improve construction quality by making contractors liable for the performance of the facility after project completion. These new and emerging contracts place an increasing pressure on decision makers in the construction industry to search for an optimal/near-optimal resource utilization plan that minimizes construction time while maximizing its quality. This creates new and pressing needs for advanced resource utilization models that are capable of optimizing the multiple and conflicting objectives of construction time, cost, and quality. Significant research advancements have been made in the area of optimizing construction resource utilization. This led to a number of optimization models. These models can be classified according to their optimization objectives into models that attempted to: • Minimize project time and/or improve resource utilization; • minimize time and cost for non-repetitive construction using time-cost trade-off analysis • minimize time and/or cost for repetitive constructionWhile the above research study seeks to provide significant contributions to the area of optimizing construction resource utilization, there has been little or no reported research focusing on multi objective models for optimizing construction time, cost, and quality.1.2 PROBLEM STATEMENT Misallocation and misperception of time factor in construction projects have resulted in the government of Nigeria paying more than necessary for many projects. Improper time assessment can also cause additional costs in the form of delays which result in poor utilization, increasing social and economic costs. Are contractors using the most appropriate resources to execute projects in Nigeria? Do they mobilize the needed resources within the approved time frame allotted to their contracts? What effects do short time periods and/ or extended time periods have on their project costs? Are there remedies to these situations? These are some of the situations that have prompted the researcher to go deep into the assessment of the cost and time impacts of public sector construction projects in Nigeria.1.3 OBJECTIVES OF THE STUDY The study had the main objective of assessing the effects of timely delivery of construction projects on the economy of Nigeria, but specifically it had the following objectives.
  1. To establish the extent to which time factors have impacted on construction of projects in the public sector in Nigeria.
  2. To find out the change in the perception of contractors on time effects on public sector construction in Nigeria.
  3. To find out the relationship between timely delivery of construction projects and the economic development of Nigeria.
1.4 RESEARCH QUESTIONS In order to achieve the objectives of the study, the following research questions were used by the researcher:
  1. What effects do time factors have on construction of projects in Nigeria?
  2. Has the perception of contractors on time factors in projects construction changed in recent years?
  3. What relationship exists between timely delivery of construction projects and economic development in Nigeria?
1.5 RESEARCH HYPOTHESIS Ho: There is no significant relationship between timely delivery of construction projects and economic development of Nigeria.Hi: There is a significant relationship between timely delivery of construction projects and economic development of Nigeria.1.6 SIGNIFICANCE OF THE STUDY All construction contracts allocate time between owners and contractors. Hence the significance of this study would better inform improved project relationships and communications and enhance construction administration practices between owners and contractors. The findings would also enhance and broaden time of wide range of risks that could materialize during the design, and construction phases of a project which would subsequently result in better and more prudent designs specifications.1.7 SCOPE OF THE STUDY The researcher will limit the study to the effects of timely delivery of construction projects on the economy of Nigeria, using the Fly Over 2 project constructed by Julius Berger in Uyo, Akwa Ibom State as a case study. Findings and recommendations by the researcher may not be used for general analysis as the researcher could not assess numerous construction projects due to time and financial constraints.1.8 LIMITATIONS OF THE STUDY Construction of projects in the public sector has assumed significant functions, hence the need for assessment on the cost and time impacts of construction of projects in order to achieve overall project objectives. Historical project schedule and duration data is treated as confidential by Julius Berger Nigeria Plc hence getting data for this study was very difficult. Data collection and analysis was therefore limited to the data received from project supervisors in the field of project construction.DEFINITION OF TERMSEconomy: An economy consists of the economic system in a certain region, comprising the production, distribution or trade, and consumption of goods and services in that region or country. An economy is the total aggregate sum of all transactions of value between two agents, such as one individual to one other individual, or between groups of individual activity, such as in organizations to other organizations, and between one nation and another nation.Construction: In the fields of architecture and civil engineering, construction is a process that consists of the building or assembling of infrastructure. Far from being a single activity, large scale construction is a feat of human multitasking. Normally, the job is managed by a project manager, and supervised by a construction manager, design engineer, construction engineer or project architect.Deliverable: Deliverable is a term used in project management to describe a tangible or intangible object produced as a result of the project that is intended to be delivered to a customer (either internal or external). A deliverable could be a report, a document, a server upgrade or any other building block of an overall project.Project management: this is the discipline of planning, organizing, motivating, and controlling resources to achieve specific goals. A project is a temporary endeavour with a defined beginning and end (usually time-constrained, and often constrained by funding or deliverables), undertaken to meet unique goals and objectives, typically to bring about beneficial change or added value.Time: This is a dimension in which events can be ordered from the past through the present into the future, and also the measure of durations of events and the intervals between them.REFERENCES
  • Frimpong, Y. (2003). Project management in developing countries: causes of delay and cost overruns in construction of groundwater projects. Unpublished Masters Research Project, University of Technology, Sydney, Australia.
  • Holt, G. D., Proverbs, D., and Love, P. E. D. 2000. ‘‘Survey findings on UK construction procurement: Is it achieving lowest cost, or value?’’ Asia Pac. Building Construct. Manage. J., 5, 13–20.

Blazingprojects Mobile App

📚 Over 50,000 Research Thesis
📱 100% Offline: No internet needed
📝 Over 98 Departments
🔍 Thesis-to-Journal Publication
🎓 Undergraduate/Postgraduate Thesis
📥 Instant Whatsapp/Email Delivery

Blazingprojects App

Related Research

Geology. 3 min read

Development of an AI-Driven Platform for Real-Time Mineral Deposit Prediction...

This research focuses on creating a computer-based system that uses artificial intelligence (AI) to predict where valuable mineral deposits might be located in ...

BP
Blazingprojects
Read more →
Geography. 4 min read

Smart GIS-based Flood Risk Mapping and Early Warning System Development...

This research focuses on developing a smart system that uses geographic information systems (GIS) to map flood risks and provide early warnings to communities v...

BP
Blazingprojects
Read more →
Food technology. 3 min read

Development of a Mobile App for Real-Time Freshness Monitoring of Fresh Produce...

This research focuses on creating a mobile application that helps farmers, vendors, and consumers monitor the freshness of fresh produce in real-time using tech...

BP
Blazingprojects
Read more →
Food Science and Tec. 2 min read

Development of an IoT-powered Sensor System for Real-Time Food Freshness Monitoring...

This research focuses on creating a smart system that uses sensors and the Internet of Things (IoT) to monitor the freshness of food in real time. Food spoilage...

BP
Blazingprojects
Read more →
Chemical engineering. 2 min read

Evaluating the Efficiency of Bio-Based Catalysts in Wastewater Treatment Processes...

What This Research Is About

This research focuses on exploring the use of natural, bio-based catalysts derived from plants or microorganisms to impr...

BP
Blazingprojects
Read more →
Fine and applied art. 4 min read

Augmented Reality Applications for Interactive Public Art Engagement...

This research focuses on how augmented reality (AR) technology can be used to make public art more engaging and interactive for viewers. Public art, such as scu...

BP
Blazingprojects
Read more →
Estate management. 4 min read

Smart Property Management Systems for Enhancing Rental Market Transparency...

This research is about developing and testing a digital system that helps manage rental properties more efficiently and transparently. The aim is to create a sm...

BP
Blazingprojects
Read more →
English and Literary. 3 min read

Digital Annotation and AI-Enhanced Literary Analysis of 21st-Century Fiction...

This research explores how digital tools and artificial intelligence (AI) can be used to analyze novels and stories written in the 21st century. It focuses on t...

BP
Blazingprojects
Read more →
Electrical electroni. 2 min read

Smart Grid Fault Detection Using Machine Learning Techniques...

This research focuses on improving the way faults are detected in smart electrical grids using machine learning techniques. Smart grids are modern electricity n...

BP
Blazingprojects
Read more →
WhatsApp Click here to chat with us