Chapter ONE
INTRODUCTION
- 1.1Introduction
- 1.2Background of Study
- 1.3Problem Statement
- 1.4Objective of Study
- 1.5Limitation of Study
- 1.6Scope of Study
- 1.7Significance of Study
- 1.8Structure of the Research
- 1.9Definition of Terms
Chapter TWO
LITERATURE REVIEW
- 2.1Overview of Public Building Total Project Cost Estimation
- 2.2Mean Component Costs Method in Project Cost Estimation
- 2.3Historical Perspectives on Project Cost Estimation
- 2.4Factors Affecting Public Building Project Cost Estimation
- 2.5Best Practices in Project Cost Estimation
- 2.6Comparative Analysis of Project Cost Estimation Methods
- 2.7Case Studies on Public Building Project Cost Estimation
- 2.8Technology and Innovation in Project Cost Estimation
- 2.9Challenges in Public Building Project Cost Estimation
- 2.10Future Trends in Project Cost Estimation
Chapter THREE
RESEARCH METHODOLOGY
- 3.1Research Methodology Overview
- 3.2Research Design and Approach
- 3.3Data Collection Methods
- 3.4Sampling Techniques
- 3.5Data Analysis Procedures
- 3.6Validity and Reliability of Data
- 3.7Ethical Considerations
- 3.8Limitations of Research Methodology
Chapter FOUR
DATA PRESENTATION AND ANALYSIS
- 4.1Analysis of Public Building Total Project Cost Estimation
- 4.2Variance in Mean Component Costs Method
- 4.3Factors Influencing Variance in Project Cost Estimation
- 4.4Comparative Analysis of Estimated vs. Actual Costs
- 4.5Case Studies on Variance in Project Cost Estimation
- 4.6Recommendations for Improving Cost Estimation Accuracy
- 4.7Implications of Variance in Project Cost Estimation
- 4.8Future Research Directions
Chapter FIVE
SUMMARY, CONCLUSION AND RECOMMENDATIONS
- 5.1Conclusion and Summary of Findings
- 5.2Recap of Research Objectives
- 5.3Contributions to Knowledge
- 5.4Practical Implications
- 5.5Recommendations for Practice
- 5.6Areas for Future Research
- 5.7Concluding Remarks
Thesis Abstract
Building construction project has become an everyday issue, and this involves the spending of hard earned money by the project owner called the client. The expectation of the owner of any building project is justification of good project delivery.Analytical and approximate variance of public building total project cost, estimation by mean component costs method.This is enabled by the objectives of the project which definitely includes project cost that envelopes the cost and quality of delivery at the expected time. The major issue, is the project cost which dictates its success. Project cost variance has been affecting the speedy and successful delivery of building construction projects. The key fact in this study method was to collect and analyse public building project cost estimates containing building components, which includes preliminaries, substructure, superstructure, mechanical/electrical, external works and contingency in the bill of quantity (BOQ) from projects handled by Education Trust Fund(ETF) in the tertiary institutions located in Kaduna, Kwara, Kogi and Abuja from 2009 to 2010. The study adopted mean component cost method modeled by Skitmore and Ng (2002) to determine the projected cost variance of the Lecture Theatres and Lecture Rooms handled by the organization in various tertiary institutions in Nigeria. The analysis of the data collected was made by using standard method of analysis which employs SPSS for the project costs.Skitmore and Ng (2002) model was employed to test the variability of the project cost data. The result shows that; the building component cost data 4782.50 had closer link to the mean 4773.92(mean) for preliminaries component column in project ID 4 of Lecture Theatreandanother component data 2797.62 is also close to 2312.91(mean) for Ext.Wkscolumn in project ID 7 for the Lecture Theatre building projects butfor the Lecture Classrooms building the preliminaries column had 1531.41 and 1416.33(mean) in project ID 2 and 1611.22 and 1673..58(mean) for M/E column for project ID 5. This project therefore concludes in addition to the results of the cost variances, that the lecture theatre and classrooms projects are underestimated.Interview was also conducted on the professional estimators in building industry. Moreover significant differences exist among the components in those public buildings.The analytical calculation shows that the correct variance for an average lecture theatre project from this research was found to be 34.73%. The sample analyzed had shown that the correct variance of the class room was found to be 38. 50%. Therefore lecture theatre is observed to be a better building project than the class room building. The study recommends the need to minimize the occurrence of the overrun by thoroughly crosschecking the initial estimate and addressing other technical issues before the contract is awarded. It also recommends the employment of the mean component cost method of analysis and setting of a committee to properly scrutinize the estimate.